§ 13.14.130. Notice—Contents.  


Latest version.
  • The notice shall specify with particularity what work is required to be done and shall state that if the said work is not completed by the affected property owner within 30 days after receipt of notice, the city engineer will perform the required work and the costs and expenses in connection therewith will be assessed against the affected property and become a lien thereon.

(Ord. 4872 § 9(c), 1968)