§ 14.06.140. Order to retrofit—Time limits.  


Latest version.
  • A.

    The owner of a URM building within the scope of this chapter shall comply with the requirements set forth herein and submit to the building official the information below for review within the prescribed time limits:

    1.

    Within 270 days after service of the order, a structural analysis, which is subject to approval by the building official and which shall demonstrate that the building meets the minimum requirements of this chapter; or

    2.

    Within 270 days after service of the order, the structural analysis and plans for structural alterations of the building to comply with this chapter; or

    3.

    Within 120 days after service of the order, plans for the installation of wall anchors and parapet braces in accordance with the requirements specified in UCBC Appendix Chapter 1, Section A110 (A & F); or

    4.

    Within 270 days after service of the order, submit an application for the demolition of the building.

    B.

    After plans are submitted and approved pursuant to this chapter, the owner shall obtain a building permit and then commence and complete the required construction or demolition with the time limits set forth in Section 14.06.180 herein. Such time limits shall begin to run from the date the order is served in accordance with Section 14.06.190.

    C.

    Applicants electing to install wall anchors and parapet braces pursuant to subsection (A)(3) above are also required to retrofit pursuant to subsection (A)(2) or demolish according to subsection (A)(4). If such election is made, the 270 day period provided for in subsections (A)(2) and (4) and the time limits for obtaining a building permit and for completing structural alterations or building demolition set forth in Section 14.06.140 shall be extended by the building official one year. Each such time limit shall begin to run from the date the order is served.

(Ord. 6581 § 2, 1994; Ord. 6560 § 4 (part), 1993)