§ 14.05.110. Issuance.  


Latest version.
  • The building official may require that grading operations and project designs be modified if delays will occur which may lead to weather-generated problems that were not adequately considered at the time the permit issued. In addition, the following conditions shall apply:

    A.

    Permit Validity. Every permit issued shall be valid for a period of not more than 1 year from the date thereof. All of the work required to be done pursuant to the grading permit shall be fully performed and completed within the time specified.

    B.

    Permit Extensions. The permittee of a valid grading permit may apply for 1 extension of such permit, not to exceed 6 months in duration. The application shall be made prior to expiration of the permit. The application shall be filed in writing with the building official who may authorize such extension, or deny it on the basis that the nature of the work has not changed.

    C.

    Suspension or Revocation. The building official may, in writing, suspend or revoke a permit issued under the provisions of this chapter whenever the permit is issued in error or on the basis of incorrect information supplied, or in violation of any ordinance or regulation or any of the provisions of this chapter.

(Ord. 7127 § 5 (part), 2007: Ord. 6483 § 2 (part), 1992)